Establishing an Iron Ore Logistics Supply Chain
Lean project management delivers a 420km iron ore supply chain on schedule, at a cost per tonne 10% below the original project budget
- 4 minutes read
Our client is an ASX-listed Australian resources company. Its subsidiary was completing the redevelopment of a vanadium mine and ore-processing facility in the Midwest region of Western Australia, where iron ore fines are produced as a by-product of vanadium crushing and smelting.
A new logistics supply chain was required to move the iron ore fines more than 420 kilometres by road from the mine site to the port. An initial shipment of 120,000 tonnes was already committed to a fixed date less than three months away, with the chain needing to scale to support 1.5 million tonnes per annum. With that date set and no supply chain yet in place, regulatory consents, partner selection, storage and stevedoring all sat on the critical path at once.
Our team was engaged to project-manage the set-up of the iron ore logistics supply chain and enable the first phase of ore shipments to commence on schedule.
The supply chain was operational and delivered on time, capable of handling the initial 120,000 tonnes, with growth plans in place to support 1.5 million tonnes of annual shipments. Cost savings of 10% per tonne were achieved against the original project budget.
10%
<3 months
120,000t
1.5mtpa
THE APPROACH
Our team commenced with an intensive diagnostic study of the supply chain development activities to establish actual progress against the committed shipment date.
The gap analysis identified four areas of the supply chain requiring urgent attention. Each sat on the critical path to first shipment, and each depended on parties outside the client’s direct control — local authorities, logistics contractors, port operators and state regulators.
The set-up programme was structured around those four areas:
- Regulatory consents: obtaining the necessary approvals from local authorities to use the roads and bridges along the 420km route.
- Transport providers: selecting the operators for the long-haul and short-haul legs, from the mine site through to the storage sheds at the port.
- Storage: identifying and securing a local storage facility at the port capable of housing the initial shipments.
- Stevedoring: selecting a provider able to achieve the minimum load rate of 500 to 600 tonnes per hour from stockpiles.
THE SOLUTION
A visual management centre was established as the foundation of the program, displaying the status of the partner selection and regulatory approval processes in a single place. With four workstreams running in parallel against a fixed shipment date, the centre gave the client’s executive team and board, and the incoming logistics partners, a shared view of progress and what was holding up the critical path.
Leading logistics providers were identified and invited to tender. A structured review process was defined with the key stakeholders, which significantly improved coordination between the parties and the speed of decision-making. Selection criteria were validated with senior management and the board of directors before the evaluation began, and a recommendations paper was prepared to help board members select the preferred business partners.
Rather than accept tender submissions at face value, we applied go-look-see to validate the claims made by the leading bidders, confirming on site that each could deliver the service levels it had tendered. Preferred logistics partners were then selected for all three legs of the supply chain.
The approvals pathway was actively managed rather than monitored. Our team coordinated the Department of Mines and Petroleum applications and challenged every aspect of the council planning and main roads approval process to reduce lead times, working in parallel with partner selection on the consents for road and bridge use along the 420km route.
In parallel, the physical infrastructure was brought into readiness. We coordinated the approvals and modification works required for the port storage facility to accept iron ore fines, and coordinated the earthworks and installation of the weighbridge on the mine site.
A master schedule was developed with the successful parties, setting out detailed plans for rapid implementation, and every supplier was challenged and supported to deliver against it. On completion, the supplier relationships for the final solution were handed to the client’s operations team to coordinate the first shipments.