Railway Occupation Program Risk Mitigation
Lean methods study reduces construction program risk and cost
- 3 minutes read
Our client was the head contractor in an alliance supporting the delivery of a $17.3b program to remove 110 railway-road level crossings across suburban Melbourne.
The state-government asset owner challenged the alliance leadership team regarding the program contingency risk in the 93-day rail corridor occupation, which was planned to deliver a $480M work package. The work package involved the construction of a 2.5km rail bridge, and the viaduct substructure and superstructure were the critical paths in the occupation program.
The program was tight due to the inherent constraints of operating in a densely populated suburban area. Completing the program during the winter months compounded the risk of bad weather. Any program overrun would create extensive commercial pressure, so a risk mitigation plan was required.
25%
3x
$5M
14x
The approach
ORBIZ facilitated an end-to-end study of the construction program scheduled for the occupation to identify overrun risks and improvement opportunities.
The study utilised a series of Lean methods to engage the project team in analysing and challenging the construction methodology and program.
The team facilitated a series of activities:
- Value Stream Map workshops visualised each step of the construction process hour-by-hour.
- The theory of Constraint principles enabled the team to understand how bottlenecks in the construction process would restrict throughput.
- Takt Time rules allowed the team to assess the imbalance between process throughput and the required construction outputs.
The solutions
The activity identified a series of requirements to mitigate program risk and opportunities to reduce overall construction costs:
- To meet the schedule, the pile cap construction process must be reduced from 58 hours per cap to 48 hours.
- The Onsite L-beam inventory must be increased from 69 units to 92 before occupation to mitigate trucking constraints and avoid a shortage that would otherwise stop the project midway through the program.
- A detailed traffic simulation was needed to identify material delivery constraints and enable the development and management of a comprehensive hourly plan throughout the occupation.
- The plan for offsite pre-cast crossheads and piers could cancelled, eliminating significant costs that provide minimal program value.